Case Study Continued

Project Scope:

The speed of getting our workforce on site, aided by an instant pipeline of products from our suppliers to Dover meant that the client's property was out of service for only a short period of time. Plus, we provided security from the first moment of arrival, so that the tenants (and neighbors) could rest assured that the situation was completely under control.
The scope of our service included:
    Roof and Rafter Replacement
    Structural Repair
    Exterior Wall Repair
    Window Replacement
    Drywall and Plaster Repair
    Second Floor and Joist Repair
    Foundation Repair
    Interior Build-out (including kitchens and dry-wall)
    Smoke Remediation (Odor removal)
    MEP code upgrades and replacements
    Mold remediation

Outcome:

The apartments were completely re-built and residences returned to their homes in less than 60 days - thanks largely to Theobald Construction Commercial Group's quick response team and ability to schedule difficult tasks simultaneously.